A case history of monitoring deep excavation wall
https://doi.org/10.37538/2224-9494-2021-2(29)-47-57
Abstract
The article presents the results of monitoring the horizontal displacements of the 15.5 m deep excavation wall made of tubular concrete piles. Actual and calculated values of the horizontal displacements of the wall are given. There is a significant increase (more than calculated) in the actual displacements of the wall towards the excavation due to the irregularity of construction order. The interpretation of the monitoring results is considered concerning the excavation wall that preserves stability. The monitoring results are suggested to be applied to the design of the excavation walls.
About the Authors
A. DzagovRussian Federation
O. Agafonova
Russian Federation
I. Anisimov
Russian Federation
References
1. СП 22.13330.2016. Основания зданий и сооружений.
2. СП 248.1325800.2016. Сооружения подземные. Правила проектирования.
3. СП 305.1325800.2017. Здания и сооружения. Правила проведения геотехнического мониторинга при строительстве.
4. СП 45.13330.2017. Земляные сооружения, основания и фундаменты.
5. Колыбин И.В. Уроки аварийных ситуаций при строительстве котлованов в городских условиях // Тр. междун. конф. по геотехнике «Развитие городов и геотехническое строительство» Санкт-Петербург, 16-18 июня 2008 года. - Геореконструкция-Фундаментпроект. СПб, 2008. С. 89-124.
Review
For citations:
Dzagov A., Agafonova O., Anisimov I. A case history of monitoring deep excavation wall. Bulletin of Science and Research Center of Construction. 2021;29(2):47-57. (In Russ.) https://doi.org/10.37538/2224-9494-2021-2(29)-47-57